OPC 400MW Combined Cycle Power Station
Location
Rotem
EPC/Main Contractor
Issa Khoury Metal Industry
Project Year
2011
Duration
1 Year
Sector
Conventional Power
Service
Installation
Engineering
Number Of Heavy Lift Jobs
Gantry Crane
2
More Case Studies
Project Overview In 2018, Orient Heavy Haulage (OHH) was awarded the transportation contract for Attarat Power Plant, which is the first oil shale-fired power project in Jordan. It is also the largest
Transport and installation of 14 units of heavy lift cargo. Cargo consisted of steam turbine generator, transformer and HRSG modules. Installation was carried out using gantry crane, jacking &