IPP2 - Qatarana Combined Cycle Power Plant
Location
Qatrana, Jordan
EPC/Main Contractor
Lotte Engineering & Construction
Project Year
2010
Sector
Conventional Power
Service
Transportation
Installation
Engineering
Port Handling
Number Of Heavy Lift Jobs

Gantry Crane
5

Skidding / Jacking
3

Transports
88
Image
Image

Image
More Case Studies
Project Overview In 2018, Orient Heavy Haulage (OHH) was awarded the transportation contract for Attarat Power Plant, which is the first oil shale-fired power project in Jordan. It is also the largest
Transport and installation of 14 units of heavy lift cargo. Cargo consisted of steam turbine generator, transformer and HRSG modules. Installation was carried out using gantry crane, jacking &