ACWA Power Zarqa Project
Orient Heavy Haulage completed the transport and installation of 81 units of heavy lift cargo including gas generators, gas turbines, steam turbine generator, transformers & HRSG modules.
Installation was carried out using gantry crane, strand jacks & Terex Crawler Crane CC 2800-1.
Location
Zarqa, Jordan
EPC/Main Contractor
SEPCOIII Electric Power Construction Corporation
Project Year
2017
Duration
1 Year
Sector
Conventional Power
Service
Transportation
Installation
Engineering
Port Handling
Storage
Number Of Heavy Lift Jobs

Gantry Crane
9

Strand Jacks
24

Crawler Crane
1

Transports
81
Image

Image

Image

Image

Image

Image

Image

More Case Studies
Project Overview In 2018, Orient Heavy Haulage (OHH) was awarded the transportation contract for Attarat Power Plant, which is the first oil shale-fired power project in Jordan. It is also the largest
Transport and installation of 14 units of heavy lift cargo. Cargo consisted of steam turbine generator, transformer and HRSG modules. Installation was carried out using gantry crane, jacking &